Education · November 18, 2026
EQUS Members: How Micro-Generation Works for You
EQUS micro-generation, step by step: Form A, the consent form, your meter, how credits land on your bill and what you still pay as a member with solar.
If Your Power Bill Says EQUS, Read This First
Most solar write-ups in Alberta assume your wires belong to FortisAlberta. If you are an EQUS member, they do not. EQUS owns the line to your yard, and EQUS is who your micro-generation paperwork goes to. The provincial rules are the same for everybody. The forms, the meter and a few of the steps are not.
This is a reference page for EQUS member-owners on an acreage, a farm or a rural business. It covers what the province allows, what EQUS asks for, what happens with your meter, how the credits land on your bill, and what you still pay. Every rule here comes from the EQUS microgeneration page, the EQUS Form A and consent form, Alberta's Micro-Generation Regulation, or the Alberta Utilities Commission's published guidance. Where we are describing how we handle a step ourselves, we say so.
The Short Version
- —You file one notice with EQUS: Form A, the Micro-Generation Notice. EQUS calls it the first step for member-owners.
- —If a solar company files it for you, a signed EQUS consent form has to go in with the application.
- —You do not need a new meter. EQUS says its smart meters are all bi-directional and already record power flowing both ways.
- —EQUS says there are no costs from EQUS if you use cumulative metering. Interval metering carries installation and monthly fees.
- —An electrical permit is required, and EQUS needs the signed inspection.
- —Your credits come from your power retailer, not from EQUS. You have to tell your retailer in writing that you are a micro-generator.
- —For a system under 150 kW, the regulation credits your exported power at the same rate your retailer charged you for energy.
That is the whole frame. The rest of this page fills in each piece.
Where EQUS Fits: Wires Owner, Not Retailer
Two different companies touch your power. One owns the poles, wires and meter. The other sells you the energy and sends the bill, or at least the energy part of it. The regulation calls the first one the owner of the electric distribution system and the second one your service provider.
EQUS is the first kind. It is a member-owned rural electrification association, and the consent form is addressed to EQUS REA LTD. If you are a member, EQUS is the wires owner for your service. That matters because the regulation sends the micro-generation notice to the wires owner. For an EQUS member that is EQUS, not FortisAlberta.
Not sure which one you have? The Alberta Utilities Commission's advice is simple: look at your utility bill. It names your distribution company. For how the same rules play out on FortisAlberta wires, see our page on solar on FortisAlberta service.
What the Province Counts as Micro-Generation
The Micro-Generation Regulation sets the test. A micro-generation generating unit has to do five things:
- —Use only renewable or alternative energy. Solar is on the list.
- —Be intended to meet all or a portion of your total annual energy consumption at your site.
- —Have a total nameplate capacity no bigger than the lesser of 5 MW or the rating of your service.
- —Supply power only to a site on property you own or lease.
- —Sit on that property, or on property you own or lease that is adjacent to it.
The second line is the one that sets your system size. The system is meant to cover your own annual use, not to sell power as a business. Form A asks for your annual consumption in kilowatt-hours for 12 months, right beside the nameplate capacity of the system.
The regulation also splits micro-generation in two. Under 150 kW is small micro-generation. From 150 kW up to 5 MW is large. Houses, acreages and most farm yards are small. The EQUS Form A flags the line in red: at 150 kW or larger, a utility engineering consultation and a stamped single-line diagram are required. The form also notes that some small projects may need an engineering consultation too.
For the general Alberta picture, our micro-generation guide covers the same regulation without the EQUS detail.
The Paperwork: Form A and the Consent Form
Form A, the Micro-Generation Notice
Form A is four pages. It asks who you are, who your consultant is if you have one, and what you are building. The project section wants the legal land description, the site ID, the service address and your retailer's name. Then the energy source, the number of inverters, the total AC nameplate capacity in kilowatts, your annual consumption, the connection voltage, and whether the service is single phase or three phase.
It also asks two yes or no questions about the inverters: whether they comply with CSA Standard C22.2 107.1, including the anti-islanding requirements, and whether they comply with UL 1741 Supplement A. Anti-islanding is the feature that shuts the system off when the grid goes down.
The supporting documents the form lists for a solar project:
- —An electrical single-line diagram of the system.
- —A site plan or pictures showing where the system sits.
- —The equipment specification from the manufacturer.
- —The applicable certification documents.
- —The electrical permit.
- —The electrical inspection report, sent in after the system is installed and inspected.
The Consent to Release to Another
EQUS holds your account information and will not hand it to a solar company on the company's say-so. Its microgeneration page is direct about it: if a third-party consultant is helping with or submitting your application, a completed Consent Form must be submitted together with the application.
The form is one page. You fill in your name, your EQUS account number and the name of the agent you are allowing EQUS to talk to. You tick whether the consent covers all your information or only part of it, and whether it expires on a date or runs until you tell EQUS otherwise in writing. Then you sign it.
How we handle it: on an EQUS job the consent form goes to you for signature at the same time as the agreement, and nothing goes to EQUS until it is signed. We put your name on the paperwork the way your EQUS bill prints it, with both the civic address and the legal land description, so the application matches the account.
Your Meter: Nothing to Change
Do you need a new meter before you can earn credits? EQUS answers that on its own page: no. Its smart meters are all bi-directional, which means they are already able to record power flowing in both directions.
The regulation says a small micro-generator gets a bi-directional cumulative meter. That is a meter that keeps two running totals, one for power in and one for power out. EQUS says there are no EQUS costs with cumulative metering. If you ask for an interval meter instead, EQUS says installation and monthly fees apply. There is a second catch in the regulation: a small system that is given an interval meter is deemed large micro-generation, and large micro-generation is credited at the pool price for each settlement interval instead of your retail rate. For a house or a farm yard, cumulative is the normal answer.
The regulation also puts the cost of metering and of connecting a micro-generation system on the wires owner. The exception is a connection the owner considers extraordinary, and the Commission has to agree before the owner can bill you for the extra.
How the Credits Work on Your Bill
Credits are a retailer matter. Form A says it plainly: to receive generation credits, you must notify your retailer or regulated rate provider once EQUS has accepted the notice. The regulation says the same thing and wants that notice in writing.
From there the regulation sets four rules for a small micro-generator:
- —Your retailer must give you net billing. Power you sent out during the billing period is netted against power you took in.
- —Exported power is credited at the rate your retailer charged you for energy at that site.
- —A credit left over in any month carries forward, for up to 12 months, to offset charges in later months.
- —At least once in each calendar year your retailer has to settle unused credits with you, by payment, by an offset against what you owe, or both.
One more line matters. A retailer may credit you at a different rate than the one above, but only if you and the retailer agree to it in writing. That is the clause a retail plan with its own export rate relies on. Which plan you pick moves your payback, so it is worth a look before the system is switched on.
A Worked Example
Put your own rate in here. For the example, say your retailer charges 12 cents per kWh for energy, and take one summer month and one winter month. The months in between are left out to keep it short.
Example only. Energy rate of $0.12 per kWh, small micro-generation, net billing.
| July: power sent out | 1,180 kWh | Credit of $141.60 |
| July: power taken in | 420 kWh | Energy charge of $50.40 |
| July: net | $91.20 credit | Carried forward |
| January: power sent out | 60 kWh | Credit of $7.20 |
| January: power taken in | 1,350 kWh | Energy charge of $162.00 |
| January: net | $154.80 charge | Before the carried credit |
| January: after July's credit | $63.60 owing | On the energy line |
Two things to notice. First, the credit only counts power that left your yard. Solar power you used in the house or the shop as it was made never reaches the meter, so it shows up as a smaller bill, not as a credit. Second, the carried credit is applied against charges for electricity only. The regulation does not let it be counted against other charges on the bill.
What You Still Pay
EQUS says it in its own FAQ: as long as your system is grid-connected, you still cover fees for electricity from the grid and all associated connection fees. The regulation backs that up. The distribution tariff on a micro-generation site is based on the power supplied into the site, and it has to be the same tariff you would be on without solar.
So solar goes after the energy you buy. It does not make the wires charges disappear. Any payback number that pretends otherwise is wrong. The honest way to run it is line by line off your own bill.
Frequently Asked Questions
Do I need EQUS approval before solar goes on my roof?
Yes. EQUS says approval makes sure the system complies with the regulations and runs safely while connected to the grid. Form A goes in first, with the single-line diagram and site plan. The electrical inspection report follows once the system is built and inspected.
How long does EQUS take to approve it?
EQUS does not publish a number, so we will not invent one. What the regulation does say: if a wires owner believes a system does not qualify as micro-generation, it has 14 days from receiving the notice to file a dispute with the Alberta Utilities Commission, and the Commission then has 30 days to decide unless it gives notice that it needs longer. The Commission's own advice is that getting all the required information to the wires owner early is what keeps a project on schedule.
Can I build bigger than I use now, for a shop or an electric truck that is coming?
The regulation ties the system to your annual consumption. The Alberta Utilities Commission's guidance is that a system is meant for existing needs, but a wires owner may consider planned load growth if you can show it is real: approved permits, equipment purchase records, engineered drawings, or an electric vehicle registration. Each case is looked at on its own. If the load is truly coming, bring the paper. Our post on sizing a system for a hobby farm walks through how the bill sets the size.
What happens to my solar when the power goes out?
It shuts off. EQUS says the system will safely disconnect during a power failure, and that keeping the house running takes additional equipment such as a transfer switch and a battery system. We cover when that is worth the money in do you need batteries with solar in Alberta.
Can I add panels later?
Yes, but tell EQUS first. EQUS asks to be informed before any modification. The regulation requires a new notice to the wires owner when the nameplate capacity changes, and Form A has a box for exactly that.
I have more than one meter on the yard. Can one system cover them?
Sometimes. The regulation allows aggregated sites: two or more sites on property owned or leased by the same customer, connected to the same distribution feeder, and enrolled with the same retailer at the same rate, or with the same regulated rate provider. Form A has room for up to four sites, with the first one as the generator and the rest as load. Whether your meters qualify comes down to the feeder and the retail accounts.
What Working With Range Road Solar Looks Like on EQUS Wires
- —Send your most recent power bill. It carries a 12-month usage graph, and that is the consumption number Form A asks for.
- —First numbers get run over the phone. A site visit happens before anything is signed. On most yards a south-facing roof is the first place we look.
- —When you sign the agreement, you sign the EQUS consent form with it.
- —We file Form A with EQUS, with the single-line diagram, site plan, equipment specifications and the inverter certificate attached. A licensed electrical contractor pulls the electrical permit.
- —We install. The electrical inspection is done and EQUS gets the signed inspection.
- —You notify your retailer in writing that you are a micro-generator, and credits start showing on the bill. We tell you when and what to send.
From signed agreement to a running system is typically two to six weeks. Our default equipment is LONGi panels on APsystems microinverters.
Get the Numbers for Your Own Yard
The rules above are the same for every EQUS member. The numbers are not. They come off your bill: what you use in a year, what you pay per kWh for energy, and what the wires charges are. Send us the bill and we will show you the system size it supports and the payback, line by line.
Call 403-367-5999 or send us your bill at rangeroadsolar.com.
Range Road Solar installs across Alberta. See Airdrie solar installer for service area details.
Ready to get a real number for your property?
Send us your most recent power bill. We'll review your consumption and give you an honest design and cost estimate. No obligation.